Sports Hall Flooring in Marcilla with Rayston Floor PU 10 Sport
Sports Hall Flooring in Marcilla with Rayston Floor PU 10 Sport in 2022. España – Navarra. The products on the job are Floortop 1K.
01 · Project overview
What is this project?
Sports Hall Flooring in Marcilla with Rayston Floor PU 10 Sport in 2022. España – Navarra. The products on the job are Floortop 1K. España – Navarra is the setting, and the exposure is what chooses the build-up.
To do so, they used Rayston Floor PU 10 Sport, a three-layer system.
Its base is Floortop 1K, a polyurethane that Krypton Chemical makes.
So the new system had to go on top of this old floor.
Krypton Chemical supplies the resin system. The duty is ordinary and strict: keep water, wear and weather on the right side of the structure, and do it in the details as well as in the open field.
| Project | Sports Hall Flooring in Marcilla with Rayston Floor PU 10 Sport |
|---|---|
| Place | España – Navarra |
| Year | 2022 |
| Line | Flooring |
| Products | Floortop 1K |
02 · The challenge
What did this structure ask of the system?
Sports Hall Flooring in Marcilla with Rayston Floor PU 10 Sport is a working floor. Wheels, washing water and the daily grit of a building all sit on the same film. A coating that only looks right on the day it is laid will map every crack in the slab within a season.
The concrete has to be opened, not painted over. Laitance, oil and old dust are how resin floors lose their bond, and they lose it in the traffic lines first. Joints and drains are details, not the edge of the job.

03 · The solution
Which system was trusted here?
The system trusted here is the one named for the job: Floortop 1K. It is chosen because it matches the substrate and the exposure, not because every building wants the same can.
A floor system is a stack. Primer for the bond, body for the thickness, seal for the face. Skipping the primer to save a day is how the floor comes back up on the tyres.
04 · Application
How is the system built?
On this floor the sequence follows the products named for the job: Floortop 1K. The slab is ground or blasted, the dust is lifted, and cracks are filled before the first resin. A primer is what locks the system into the pores. The body coat takes the wear. The seal is the face people walk on, and it is the layer that has to keep its colour.
Each coat has to be down at the thickness that product is designed for, including at the drains and the joints. A floor that is thick in the middle and starved at the edge will fail at the edge. Traffic waits until the seal has cured. Washing water waits longer than footsteps.
On Sports Hall Flooring in Marcilla with Rayston Floor PU 10 Sport the floor is not a decorative coat. It is the surface the building works on. Preparation decides it. Oil, laitance and a closed power-floated face will take a primer for a week and then let it go. The mechanical opening of the pores is part of the system, not a favour the applicator adds if there is time.
Joints move. A resin that is rigid across a joint will crack there, and the crack fills with wash water. The joint is either honoured, with a flexible seal of the right width, or the floor design accepts a cut. Drains are turned into the floor, not left as a ring of mastic after the last coat. Colour goes in the seal coat so a repair later can be matched, and so daylight and cleaning chemicals meet a film that was chosen for that, not the structural coat underneath.
Cure is part of the programme. Foot traffic, pallet trucks and the first wash are three different dates. Opening a floor early because the building is in a hurry is how a good system gets a bad name. The data sheet of each named product sets those dates. This page does not invent a shorter one for the sake of the story.
05 · Results
What does a job like this stand behind?
Sports Hall Flooring in Marcilla with Rayston Floor PU 10 Sport has one standard. The coating is still doing its job after the building is back in use, at the details as well as in the middle.
Figures for cure, thickness and strength, where they are given, come from the product data sheets. They are not a test cut out of this building.
What this asks of Sports Hall Flooring in Marcilla with Rayston Floor PU 10 Sport is workmanship at the difficult line. The open field is the easy part of a resin job. Outlets, edges, penetrations and changes of plane are where thickness goes missing, and where water or wear finds the gap. The same products and the same care belong there, and the cure is allowed to finish before the building goes back into use. That is the difference between a coating that was simply applied and a system that stays in service.
06 · Products
Products on this job
Floortop 1K
Named on this project. The data sheet carries the application window and the typical figures.
07 · FAQ
Frequently asked questions
Where is this project?
Sports Hall Flooring in Marcilla with Rayston Floor PU 10 Sport. España – Navarra
When was the work done?
2022.
Which products were used?
Floortop 1K.
Why does the concrete preparation matter?
Resin sticks to a clean, open slab. It does not stick to laitance or oil. The bond fails in the wheel tracks first.
When can the floor take traffic?
Foot traffic waits until the seal has cured. Wheels and wash-down wait longer. The exact window is the one in each product’s data sheet.
08 · Photos
On site