Home → Applications → Biogas digesters
Biogas digesters
Biogas digesters require a continuous waterproofing and chemical-resistant barrier matched to biogas, slurry, substrate movement and maintenance. This engineering guide frames the application intent without replacing the current system specification or product technical data sheet.
DATA SHEET · Krypton ProLine MFE 100
DATA SHEET · Krypton ProLine CH55
DATA SHEET · Krypton ProLine PU 1000 TC
Use and application
The application intent is waterproofing of biogas digesters. Qualify the gas and slurry exposure, tank geometry, service temperature, cleaning regime, substrate and maintenance constraints. For a typical Krypton reference stack, Krypton ProLine MFE 100, Krypton ProLine CH55 and Krypton ProLine PU 1000 TC are reference points from the aligned kit, not an automatic system selection. Compare the current Products and Systems documentation, and use the associated application context at Digesters wwtps to keep the scopes distinct.
01
Gas, slurry and tank substrates
Exposure differs between the gas space, slurry zone and external faces of the tank. Concrete brings porosity, alkalinity, moisture and cracking risks; metal tanks require controlled preparation and corrosion management. Joints, shell-to-base transitions, penetrations, mixers, feed connections, discharge connections and inspection points need a continuous, documented detail.
02
Layers and references
Define the sequence from prepared concrete or metal substrate through Krypton ProLine MFE 100 primer, Krypton ProLine CH55 functional membrane or lining, and Krypton ProLine PU 1000 TC where the specified system requires a finish or protection layer. Verify chemical compatibility, preparation, mixing, consumption, thickness, overcoat windows and cure against the current technical data sheet; the Calculator supports quantities, while Systems establishes the applicable route.
03
Common mistakes
- Treating gas-space exposure and slurry immersion as the same service condition without checking chemical compatibility and temperature.
- Applying over damp, contaminated or weak concrete, or over inadequately prepared metal, without a documented preparation and moisture check.
- Omitting joints, penetrations, mixers, feed connections, discharge connections and terminations, or closing the lining before checking continuity, adhesion, thickness, pinholes and cure.
04
Operating sequence
1. Record the gas and slurry zones, chemistry, temperature, cleaning regime, dimensions and service scenario. 2. Survey concrete or metal condition and map joints, transitions, penetrations, mixers, feed connections, discharge connections and repair areas. 3. Select a compatible route in Systems and verify the MFE 100, CH55 and PU 1000 TC sequence, if applicable, against the current technical data sheets. 4. Calculate quantities with the Calculator. 5. Approve a representative area, document preparation and application controls, inspect continuity and release the digester only when the project requirements are met.